We are working around the clock as construction continues to advance at La Rosa VI. Using the latest technology and modern construction methods, we look forward to delivering this phase at Villanova. The progress is monitored by us and aligned with the Dubai Real Estate Regulatory Agency (RERA).

With significant progress recently, we would like to highlight the following:

- European sanitary fittings set
- Fire Alarm system installed
- Thermal Expansion Valve technology for all AC units installed
- Pullable ladder fitted
- Dubai Civil Defence approvals obtained


Q3 2023 Construction Progress

Overall Progress Icon
إجمالي التقدم المحرز
%88
As of 25/10/23
Landscape Progress Icon
إجمالي التقدم المحرز في المناظر الطبيعية
%4
Infrastructure Progress Icon
إجمالي التقدم المحرز في البنية الأساسية
%100

According to our internal inspection conducted on October 25th, the project’s progress is 87.62%As per RERA, the progress is reported as 62.66 % based on their inspection conducted on July 24th.

 
 
 

سجل الآن

الرجاء إدخال الإسم الأول
الرجاء إدخال الإسم الثاني
الرجاء إدخال رقم هاتف صحيح (e.g. 50xxxxxxx)
الرجاء إدخال بريد إلكتروني صحيح
هل أنت وسيط؟:      

شكراً لك
لقد تم إرسال الرسالة بنجاح.




Loading...
whatsapp