Construction Advances Steadily at La Violeta 1

We are pleased to provide an update on the construction of your new home at La Violeta 1, within the family-friendly master community of Villanova. We are excited for you and your family to begin a new chapter where you can enjoy life to the fullest beyond four walls in the heart of Dubailand.

The construction is on track with the completion of precast work, which includes the installation of prefabricated concrete panels for structural support.

We have also completed the floor tiling work, which elevated the ambience of your home. Additionally, work on internal finishing and mechanical, electrical and plumbing (MEP) is progressing well, bringing us one step closer to delivering your beautifully crafted home.

The latest developments onsite have been summarised below:

- Precast work is complete.
- Floor tiling is complete.
- Internal finishing work is in progress.
- Mechanical, electrical and plumbing (MEP) is in progress


*Q2 2024 Construction Progress

Overall Progress Icon
Overall Progress
86.4%

*Based on our internal inspection on 23/05/2024, the project is 86.4% complete. RERA's inspection conducted on 09/05/2024 reported a progress of 73.48%.

 
 
 

REGISTER NOW

Please enter valid First name
Please enter valid Last name
Please enter valid mobile number (e.g. 50xxxxxxx)
Please enter valid Email
Are you a broker?:      

Thank You
Thank you for registering your interest!
Due to scheduled system maintenance from 4 PM on January 29 to February 2, 2025, there may be a delay in receiving your confirmation email and call back.
Rest assured, our team will contact you as soon as the system maintenance is complete.




Loading...
whatsapp